Your next project consists of 8 consecutive 8-day activities,each estimated by a different worker in your organization.Your organizational culture dictates that you add your own safety margin of 3 days into your estimates.Unbeknownst to you,the project manager has recently converted to a critical chain project management view.The project manager knows perfectly well what sorts of games are played with activity estimates and she knows exactly how much activity padding takes place.What will the overall project safety margin be once the project manager reviews your estimates and makes the project schedule?
A) 12 days
B) 6 days
C) 18 days
D) 9 days
Correct Answer:
Verified
Q52: A project consists of four activities
Q53: A project consists of four activities
Q54: What is aggregated buffer and how can
Q55: Which statement about critical chain methodology is
Q56: Once the organization elevates its constraint,its system
Q58: The critical chain is usually the same
Q59: A project consists of four activities
Q60: Which statement about critical chain project management
Q61: A project is represented by the
Q62: A project consists of four consecutive
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents