Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
A) The project manager cannot force subcontractors to use this project management approach.
B) The feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) Subcontractors routinely operate according to calendar delivery dates.
D) The corporate culture of "no blame" does not naturally extend to subcontractors.
Correct Answer:
Verified
Q75: A project consists of six consecutive
Q76: A project is represented by the
Q77: The buffers supplied to non-critical paths in
Q78: A project is represented by the
Q79: A project is represented by the
Q81: A resource constraint can be exploited using
Q82: A project that consists of six
Q83: An important element in critical chain scheduling
Q84: Drum buffers are:
A)A safety margin separating different
Q85: What are the implications for due dates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents