An ex-gratia claim made when a project is closed down is made when:
A) There is no contractual basis for a claim.
B) The project company fails to perform to the terms of the contract.
C) The client company fails to perform to the terms of the contract.
D) A third party causes either the client or project company to fail to perform to the terms of the contract.
Correct Answer:
Verified
Q72: The rapid evolution of technology and the
Q73: Construction of the largest egg in the
Q74: Projects accumulate quantities of unused supplies and
Q75: The Microserf was in a blind panic;now
Q76: When a project is shut down,the project
Q78: An example of an external intellectual issue
Q79: In non-binding arbitration:
A)The judge can offer suggestions
Q80: An internal intellectual issue that arises when
Q81: Arbitration refers to the formalized system for
Q82: A final report section on the techniques
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents