You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information,which one of the following statements is correct?
A) You should accept project B since it has the higher IRR and reject project A because you can not accept both projects.
B) You should accept project A because it has the lower NPV and reject project B.
C) You should accept project A because it has the higher NPV and you can not accept both projects.
D) You should accept project B because it has the higher IRR and reject project A.
E) You should accept both projects if the funds are available to do so since both NPV's are > 0.
Correct Answer:
Verified
Q69: You are considering a project with an
Q70: You would like to invest in the
Q71: A project has an initial cost of
Q72: You are considering two mutually exclusive projects
Q73: A project will produce cash inflows of
Q75: Ginny Trueblood is considering an investment which
Q76: A project has an initial cost of
Q77: It will cost $3,000 to acquire a
Q78: What is the profitability index for an
Q79: Based on the profitability index (PI) rule,should
Unlock this Answer For Free Now!