Sid contracts to put new kitchen cabinets in Ned's house.Sid repeatedly tries to install the cabinets,but Ned does not grant him access to the house.In this case:
a.Ned is discharged from his duties under the contract because of material breach.
b.the frustration of purpose doctrine applies to discharge the contract.
c.Sid is discharged from his duties under the contract because Ned's prevention of Sid's performance constitutes a material breach.
d.Both Sid and Ned are discharged from their duties because of impossibility of performance.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q44: On November 1, Paula and Roberta enter
Q47: Rebecca sees a pair of beautiful silver
Q58: Unless one of the parties contractually assumes
Q62: Louis agreed to provide all the apples
Q62: Explain what may constitute a material breach
Q64: Russell contracts to install for Nina her
Q68: Al owes Tracy $500, due June 1.
Q68: Russell and Joe make a contract for
Q69: Milt built a barn for the Lowreys,
Q70: What is a condition? Give an example
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents