For line balancing,cycle time is computed as:
A) daily operating time divided by the desired output.
B) desired output divided by the daily operating time.
C) daily operating time divided by the product of the desired output and the sum of job times.
D) the product of desired output and the sum of job times divided by daily operating time.
E) 1.00 minus station time.
Correct Answer:
Verified
Q122: The maker of the world-famous Widget needs
Q123: The maker of the world-famous Widget needs
Q124: A company is designing a product layout
Q125: QRS Corp.is designing a product layout for
Q126: A company needs to rebalance a product
Q128: A company is designing a product layout
Q129: Using the method developed by Richard Muther,which
Q130: QRS Corp.is designing a product layout for
Q131: The maker of the world-famous Widget needs
Q132: The maker of the world-famous Widget needs
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents