The advantage(s) the PERT/CPM technique has over a Gantt chart is (are) :
A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it indicates which activities are most critical.
D) it indicates the implications of delays in activities.
E) all of the choices are correct.
Correct Answer:
Verified
Q27: Only activities on the critical path are
Q44: Which of the following is a part
Q49: Which of the following would probably not
Q50: Which of the following are advantages of
Q51: A hierarchical listing of what must be
Q52: Scope creep refers to the tendency for
Q55: Which of the following is not a
Q58: Which of the following is not involved
Q64: A relatively simple tool for planning and
Q76: Besides project activities,the primary information that all
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents