What is the critical path?
A) The path from resource to task that passes through all critical components of a project plan
B) The path between tasks to the projects finish that passes through all critical components of a project plan
C) The path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
D) The path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time
Correct Answer:
Verified
Q19: Who is the person or group who
Q23: Project _ are any measurable, tangible, verifiable
Q24: A kill switch is a trigger that
Q41: Which of the following does a project
Q73: A(n) _ is a temporary endeavor undertaken
Q77: What do SMART criteria for successful objective
Q89: Which of the following is not a
Q91: In a Gantt chart, tasks are listed
Q98: An organization must identify what it wants
Q241: What is an internal department that oversees
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents