Worrell Corporation has a job-order costing system.The following debits (credits) appeared in the Work in Process account for the month of March:
Worrell applies overhead at a predetermined rate of 90% of direct labour cost.Job No.232,the only job still in process at the end of March,has been charged with manufacturing overhead of $2,250.What was the amount of direct materials charged to Job No.232?
A) $2,250.
B) $2,500.
C) $4,250.
D) $9,000.
Correct Answer:
Verified
Q49: Beaver Company used a predetermined overhead rate
Q50: The Cost of Goods Manufactured for March
Q51: CR Company has the following estimated costs
Q52: What was the amount of direct materials
Q53: Sweet Company applies overhead to jobs on
Q55: The cost of goods manufactured for February
Q56: Jimbob Co.has the following estimated costs for
Q57: The balance in White Company's Work in
Q58: Knowlton Company applies overhead to completed jobs
Q59: Under Lamprey Company's job-order costing system,manufacturing overhead
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents