The project defined by the following decision tree has a required discount rate of 17 percent.
What is the Time 0 net present value of a successful test and investment?
A) $21,565,903
B) $26,997,143
C) $32,288,788
D) $16,997,143
E) $42,997,143
Correct Answer:
Verified