At a production level of 7,500 units,a project has earnings before interest and taxes of $48,310.Depreciation is $9,700,and fixed costs are $12,200.What is the variable cost per unit if the sales price per unit is $29.50?
A) $21.43
B) $24.07
C) $17.76
D) $18.92
E) $20.14
Correct Answer:
Verified