What are factors considered to be true, real, or certain without proof or demonstration?
A) Project plan
B) Project constraints
C) Project assumptions
D) Project deliverable
Correct Answer:
Verified
Q52: What are specific factors that can limit
Q53: What are quantifiable criteria that must be
Q54: What are characteristics of tangible benefits?
A) Difficult
Q55: What defines the how, what, when, and
Q56: What defines the specifications for product/output of
Q58: What defines all project roles and indicates
Q59: What represents key dates by which a
Q60: What statement links the project to the
Q61: What is a status report?