Harrington Corporation produces three products, A, B, and C. Pertinent information on these products is as follows:There are 150 direct labor hours available. Machine-hour capacity allows 100 anchor bolts, only; 50 bearings, only; 40 casters, only; or any combination of the three that does not exceed the capacity.
The direct labor hour constraint for Harrington's linear programming model is:
A) A + B + C ≤ 150.
B) Min Z = 2A + 2B + 3C.
C) Max Z = 2A + 2B + 3C − 150.
D) 100A + 50B + 40C ≤ 1,050.
E) 2A + 2B + 3C ≤ 150.
Correct Answer:
Verified
Q112: Quinta Inc. manufactures machine parts for aircraft
Q113: The Multi Resource Company manufactures two lines
Q114: Harrington Corporation produces three products, A, B,
Q115: Copeland Inc. produces product X-547 in a
Q116: Which one of the following is most
Q118: Quinta Inc. manufactures machine parts for aircraft
Q119: Harrington Corporation produces three products, A, B,
Q120: Manders Manufacturing Corporation uses the following model
Q121: What strategic factors/considerations are generally relevant to
Q122: Motor Corp.manufactures machine parts for boat engines.The
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents