A company's production process has an 80 percent learning curve rate. The process has produced 1,000 units to date. A process refinement is estimated to allow a future learning curve rate for the identical product of 75 percent. However, the initial unit made using the new process will take the same amount of time as the initial unit produced using the old process. At what point, using the new process, will the production rate exceed the production rate achieved by the old process?
A) Before the 50th unit
B) Before the 80th unit
C) Before the 100th unit
D) Before the 120th unit
E) Before the 250th unit
Correct Answer:
Verified
Q47: Which of the following is a reason
Q48: You are a consultant specializing in estimating
Q49: A company can produce a small lot
Q50: The learning curve percent and the reduction
Q51: The 50th repetition of a job is
Q52: A company's production process has an 85
Q53: A company can produce a small lot
Q54: The general guidelines provided in the textbook
Q55: The 50th repetition of a job is
Q56: The 10th repetition of job is timed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents