A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented here: Using CPM, which activities make up the critical path?
A) A, B, D, F, G
B) A, C, E, F, G
C) A, C, B, F, E
D) A, D, E
E) None of these
Correct Answer:
Verified