A Liquidated Damages Provision Will Be Enforced Only When

Question 26

Multiple Choice

A liquidated damages provision will be enforced only when:


A) the subject matter of the contract has a value which cannot be put in monetary terms.
B) the amount specified is reasonable and actual damages would be difficult to determine.
C) the nature of the contract is such that damages would not be difficult to determine.
D) the amount agreed on is not the injured party's only remedy.