A manufacturer planned to use $82.00 of materials per unit produced, but in the most recent period it actually used $80.00 of material per unit produced. During this same period, the company planned to produce 1,200 units, but actually produced only 1,000 units. The flexible-budget variance for materials, to the nearest dollar, is:
A) $2,000 favorable.
B) Impossible to determine without additional information.
C) $14,000 unfavorable.
D) $16,400 unfavorable.
E) $2,400 unfavorable.
Correct Answer:
Verified
Q36: For a direct material, which one of
Q37: The way managers and employees who are
Q38: Which one of the following, for each
Q39: The difference between the actual sales volume
Q40: For improved financial control, a standard cost
Q42: Which of the following is not a
Q43: Which of the following is not indicated
Q44: Customer-response time (CRT) is usually defined as:
A)
Q45: The effect on sales, expenses, or operating
Q46: Which of the following is not considered
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents