Question 102

Multiple Choice

The economic break-even point of a project can be found by:


A) setting the discount rate equal to the DOL.
B) solving for the annual sales that will equate total revenue with total cost.
C) solving for the annual sales that will give the project an NPV of zero.
D) solving for the level of sales that will give the project an IRR of zero.

Correct Answer: