What is the probability that this project will be completed within 130 days?
A) .8413
B) .90
C) .9544
D) .9772
E) .9987
Correct Answer:
Verified
Q108: Activity J has a duration of 7
Q114: What is the estimated slack time for
Q115: What is the estimated slack time for
Q116: What is the estimated expected (mean) time
Q117: What is the estimated expected (mean) time
Q118: What is the estimated expected (mean) time
Q120: What is the estimated expected (mean) time
Q122: What is the probability that the critical
Q123: In crashing this project to 18 weeks,
Q124: In crashing this project, which activity should
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents