What is the probability that the critical path for this project will be completed within 200 days?
A) 0.8413
B) 0.9544.
C) 0.9772
D) 0.9974
E) 0.9987
Correct Answer:
Verified
Q106: What is the probability that the critical
Q107: What is the estimated standard deviation in
Q108: What is the estimated expected (mean) time
Q109: What is the estimated slack time for
Q110: What is the estimated slack time for
Q112: What is the estimated standard deviation in
Q113: What is the estimated expected (mean) time
Q114: What is the estimated slack time for
Q115: What is the estimated slack time for
Q116: What is the estimated expected (mean) time