Which of the following lead to simulation being a useful tool with uncertain activity times.
A) paths that aren't independent
B) activity times that aren't deterministic
C) activity times that can't be crashed
D) non-critical paths that have no variability
E) critical paths with activities with deterministic time estimates
Correct Answer:
Verified
Q108: Activity J has a duration of 7
Q122: What is the probability that the critical
Q123: In crashing this project to 18 weeks,
Q124: In crashing this project, which activity should
Q125: What activities make up the critical path?
Q127: What are the estimated slack times (in
Q128: What are the estimated standard deviations (in
Q129: What is the estimated expected (mean) time
Q130: What is the total cost of reducing
Q131: What is the total cost of reducing
Unlock this Answer For Free Now!