A job is expected to have a learning curve of 90 percent.The third unit required 16 hours.The twelfth unit should take approximately how many hours?
A) 2.67
B) 4.83
C) 7.94
D) 10.31
E) 12.95
Correct Answer:
Verified
Q24: A learning rate of 77% will produce
Q28: A job has a 70% learning curve.If
Q32: It took exactly 10 hours to perform
Q62: Once production is underway and the learning
Q66: To which worker would learning curves be
Q70: Increasing volumes result in _ the learning
Q77: On a log-log graph, learning curves appear
Q85: A job has an 80 percent learning
Q90: In which of the following managerial activities
Q99: Which one of the following would learning