In a stopwatch time study, the number of cycles that must be timed is a function of:
A) the variability of observed times
B) the desired accuracy for the estimated job time
C) the desired confidence for the estimated job time
D) all of the above
E) none of the above
Correct Answer:
Verified
Q59: "Time-based systems" compensate employees according to the
Q60: The Occupational Safety and Health Act (OSHA)
Q63: The methods analysis chart which describes the
Q64: Output-based systems compensate employees according to the
Q64: The symbols for operation, storage, transportation, inspection,
Q65: In methods analysis, a therblig is a:
A)
Q65: The chart used to review the overall
Q66: Determining the number of cycles to observe
Q79: It would be acceptable to use a
Q127: Which of the following concerns is not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents