The percent complete index that looks at percent complete in terms of budgeted amounts is calculated by which of the following?
A) EV/BAC
B) (EV-PV) /BAC
C) AC/EAC
D) (EV-AC) /BAC
E) (EV-PV) /EAC
Correct Answer:
Verified