Roger is new-product project manager for a retail company.Recently the team has exhibited a high degree of conflict over who will control the group and how decisions will be made.Which stage of development is the team in?
A) Norming
B) Storming
C) Performing
D) Adjourning
E) Forming
Correct Answer:
Verified