An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.
A) Random chance
B) A disaster
C) Risk
D) Hazard
E) Bad luck
Correct Answer:
Verified
Q5: The attempt to recognize and manage potential
Q7: The initial step in the risk management
Q8: The cost impact of a risk event
Q9: The easiest and most commonly used technique
Q10: The 1999 NASA Mars Climate Orbiter is
Q11: Which of the following is not one
Q12: Which of the following would not be
Q15: All of the following are included in
Q18: A risk profile is a list of
Q19: One of the keys to success in