Given That a Project Closely Follows Past Projects in Features

Question 46

Short Answer

Given that a project closely follows past projects in features and costs, the ________ method of assigns costs and times to particular phases that a project will go through.

Correct Answer:

verifed

Verified

apportion
Explanation: This method is an...