MegaComputers, Inc

Question 13

Multiple Choice

MegaComputers, Inc.has assigned a project manager for each of the five new-product teams.The managers as well as the project team members work on the projects on a full-time basis.The structure being used is ________ organization.


A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project

Correct Answer: