Tina,an experienced pool contractor,and Bruce agree on a price for Tina to build a pool in Bruce's backyard.Tina discovers that she did not initially figure in enough of a charge for labor.She tells Bruce that unless she receives an extra $5,000 with which to hire workers,she cannot complete the job.Bruce agrees thinking to himself that he has a way out.When Tina finishes the pool,Bruce refuses to pay the additional $5,000.Which of the following is the most likely result of their dispute?
A) Bruce will be required to pay because a typical, unilateral contract is involved, and he got the benefit of his bargain.
B) Bruce will be required to pay because a typical, bilateral contract is involved, and he got the benefit of his bargain.
C) Bruce will be required to pay because unforeseen circumstances are an exception to the preexisting duty rule.
D) Bruce will not be required to pay because he provided no additional consideration, and the preexisting duty rule applies.
E) Bruce will only be required to pay ½ of the agreed upon amounts because of the calculations involved under the preexisting duty rule.
Correct Answer:
Verified
Q49: What is Credit Card Company A's best
Q50: Which of the following is true regarding
Q51: In a lawsuit between the bank and
Q55: Which of the following is true regarding
Q56: Christen graduates from college,receives a job offer
Q57: Which of the following was involved when
Q58: Which of the following is true regarding
Q64: Assuming no exception applies, which of the
Q68: Which of the following is true regarding
Q86: Define and discuss promissory estoppel, and give
Unlock this Answer For Free Now!