Patricia Has Requested Extra Payment Because Abnormal Subsurface Rock Formations

Question 58

Multiple Choice

Patricia has requested extra payment because abnormal subsurface rock formations made excavation on the construction site far more costly and time-consuming than could have been reasonably expected.The court will:


A) enforce such modifications in contract.
B) allow the party to rescind such a contract.
C) consider the contract voidable.
D) consider the contract unenforceable.