Geronimo, Inc. is considering a project that has an initial outlay or cost of $220,000. The respective future cash inflows from its four-year project for years 1 through 4 are: $50,000, $60,000, $70,000, and $80,000, respectively. Geronimo uses the internal rate of return method to evaluate projects. Will Geronimo accept the project if its hurdle rate is 10%?


A) Geronimo will not accept this project because its IRR is about 9.70%.
B) Geronimo will not accept this project because its IRR is about 8.70%.
C) Geronimo will not accept this project because its IRR is about 6.50%.
D) Geronimo will not accept this project because its IRR is about 4.60%.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents