Who is a project manager?
A) The application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project
B) Any measurable, tangible, verifiable outcome, result, or item that is produced to complete a project or part of a project
C) Represent key dates when a certain group of activities must be performed
D) An individual who is an expert in project planning and management
Correct Answer:
Verified
Q41: Which of the following does a project
Q44: What is a project?
A) A temporary endeavor
Q54: Which of the following is a characteristic
Q62: Which of the following is not a
Q72: What is project scope?
A) Quantifiable criteria that
Q73: Which of the following is not a
Q88: What is the most important part of
Q92: An organization must identify what it wants
Q98: An organization must identify what it wants
Q99: What is a graphical network model that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents