When the present value of the cash inflows exceeds the initial cost of a project,then the project should be:
A) accepted because the internal rate of return is positive.
B) rejected because the net present value is negative.
C) rejected because the internal rate of return is negative.
D) accepted because the profitability index is negative.
E) accepted because the profitability index is greater than 1.
Correct Answer:
Verified
Q21: The discounted payback period of a project
Q22: When two projects both require the total
Q24: No matter how many forms of investment
Q25: Given that the net present value (NPV)is
Q27: If you want to compare the present
Q28: The internal rate of return for a
Q29: The internal rate of return (IRR): I.
Q30: Matt is analyzing two mutually exclusive projects
Q36: Analysis using the profitability index:
A)frequently conflicts with
Q368: Which one of the following is the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents