These are all guidelines a project manager should consider when assigning project work EXCEPT
A) Select people with compatible work habits and personalities.
B) Always assign the best people to the most difficult tasks.
C) When possible,team veterans up with new hires.
D) Select individuals with skillsets that complement each other.
E) Have people work together early so that they can become familiar with each other.
Correct Answer:
Verified
Q5: In a resource-constrained project, the first priority
Q7: If resources are not adequate to meet
Q25: Splitting an activity can result in all
Q32: All of the following are benefits of
Q38: A(n)_ constraint addresses the sequence in which
Q41: If three copiers are needed to produce
Q44: A shortage of programmers to write software
Q50: The shortage of computer chips to produce
Q59: Resource dependency takes priority over the technological
Q60: Trying to renovate a ship compartment that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents