Stephenson Company's computer system recently crashed,erasing much of the Company's financial data.The following accounting information was discovered soon afterwards on the CFO's backup computer disk. Stephenson Company's computer system recently crashed,erasing much of the Company's financial data.The following accounting information was discovered soon afterwards on the CFO's backup computer disk.   Direct labor cost incurred during the period amounted to 1.5 times the factory overhead.The CFO of Stephenson Company has asked you to recalculate the following accounts and report to him by week's end.What should be the amount of direct materials used? A) $8,500. B) $7,000. C) $12,500. D) $2,000. $8,500 = $35,500 + $73,500 + X + $49,000 - $126,000 = $40,500; Where $73,500 = (1.5 x Overhead) ;X = $8,500
Direct labor cost incurred during the period amounted to 1.5 times the factory overhead.The CFO of Stephenson Company has asked you to recalculate the following accounts and report to him by week's end.What should be the amount of direct materials used?


A) $8,500.
B) $7,000.
C) $12,500.
D) $2,000.
$8,500 = $35,500 + $73,500 + X + $49,000 - $126,000 = $40,500;
Where $73,500 = (1.5 x Overhead) ;X = $8,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents