Solved

Demski Company Has Used a Two-Stage Cost Allocation System for Many

Question 130

Essay

Demski Company has used a two-stage cost allocation system for many years.In the first stage,plant overhead costs are allocated to two production departments,P1 and P2,based on machine hours.In the second stage,Demski uses direct labor hours to assign overhead costs from the production departments to individual products A andB.
Budgeted factory overhead costs for the year are $300,000.Both the budgeted and actual machine hours in P1 and P2 are 12,000 and 28,000 hours,respectively.
After attending a seminar to learn the potential benefits of adopting an activity-based costing system (ABC),Ted Demski,the president of Demski Company,is considering implementing an ABC system.Upon his request,the controller at Demski Company has compiled the following information for analysis:
Demski Company has used a two-stage cost allocation system for many years.In the first stage,plant overhead costs are allocated to two production departments,P1 and P2,based on machine hours.In the second stage,Demski uses direct labor hours to assign overhead costs from the production departments to individual products A andB. Budgeted factory overhead costs for the year are $300,000.Both the budgeted and actual machine hours in P1 and P2 are 12,000 and 28,000 hours,respectively. After attending a seminar to learn the potential benefits of adopting an activity-based costing system (ABC),Ted Demski,the president of Demski Company,is considering implementing an ABC system.Upon his request,the controller at Demski Company has compiled the following information for analysis:    Demski manufactures two types of product,A and B,for which the following information is available:    Required: (1)Determine the unit cost for each of the two products using the traditional two-stage allocation method.Round calculations to 2 decimal places. (2)Determine the unit cost for each of the two products using the proposed ABC system. (3)(a)Compare the unit manufacturing costs for product A and product B computed in requirements 1 and 2.Why do two the cost systems differ in their total cost for each product? (b)Why might these differences be important to the Demski Company? Please see Feedback for answers. Demski manufactures two types of product,A and B,for which the following information is available:
Demski Company has used a two-stage cost allocation system for many years.In the first stage,plant overhead costs are allocated to two production departments,P1 and P2,based on machine hours.In the second stage,Demski uses direct labor hours to assign overhead costs from the production departments to individual products A andB. Budgeted factory overhead costs for the year are $300,000.Both the budgeted and actual machine hours in P1 and P2 are 12,000 and 28,000 hours,respectively. After attending a seminar to learn the potential benefits of adopting an activity-based costing system (ABC),Ted Demski,the president of Demski Company,is considering implementing an ABC system.Upon his request,the controller at Demski Company has compiled the following information for analysis:    Demski manufactures two types of product,A and B,for which the following information is available:    Required: (1)Determine the unit cost for each of the two products using the traditional two-stage allocation method.Round calculations to 2 decimal places. (2)Determine the unit cost for each of the two products using the proposed ABC system. (3)(a)Compare the unit manufacturing costs for product A and product B computed in requirements 1 and 2.Why do two the cost systems differ in their total cost for each product? (b)Why might these differences be important to the Demski Company? Please see Feedback for answers. Required:
(1)Determine the unit cost for each of the two products using the traditional two-stage allocation method.Round calculations to 2 decimal places.
(2)Determine the unit cost for each of the two products using the proposed ABC system.
(3)(a)Compare the unit manufacturing costs for product A and product B computed in requirements 1 and 2.Why do two the cost systems differ in their total cost for each product?
(b)Why might these differences be important to the Demski Company?
Please see Feedback for answers.

Correct Answer:

verifed

Verified

blured image
Demski manufactures two types of produ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents