Bryan Inc.produces a specialty top-quality juice machine.The product,the JM50,requires four processes to be completed.Specifically,these processes are exterior construction,pulp filter insertion,painting,and packaging.Each process is performed at separate workstations with different completion rates:
Exterior construction can manufacture 100,000 juicer exteriors per day.
Pulp filter insertion can install 25,000 filters every 6 hours.
Painting can decorate 3,000 juicers every half hour.
Packaging can package 5,000 juicers per hour.
The plant operates 24/7,24 hours a day every day of the week.
Which function(s) is/are the bottleneck(s) ?
A) Exterior construction and pulp filter insertion.
B) Pulp filter insertion.
C) Painting.
D) Packaging.
E) Exterior construction.
Correct Answer:
Verified
Q25: The management accountant at Iang Manufacturing Co.collected
Q26: Quality Industries manufactures large workbenches for
Q27: Ken Yalters,the COO of FreshSkin,asked his cost
Q28: Lens Care Inc.(LCI)manufactures specialized equipment for polishing
Q29: Quality Industries manufactures large workbenches for industrial
Q31: In order to reduce costs so as
Q32: Lens Care Inc.(LCI)manufactures specialized equipment for polishing
Q33: Lens Care Inc.(LCI)manufactures specialized equipment for polishing
Q35: Lens Care Inc. (LCI) manufactures specialized equipment
Q35: The management accountant at Jang Manufacturing Co.collected
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents