Bryan Inc.produces a specialty top-quality juice machine.The product,the JM50,requires four processes to be completed.Specifically,these processes are exterior construction,pulp filter insertion,painting,and packaging.Each process is performed at separate workstations with different completion rates:
Exterior construction can manufacture 100,000 juicer exteriors per day.
Pulp filter insertion can install 25,000 filters every 6 hours.
Painting can decorate 3,000 juicers every half hour.
Packaging can package 5,000 juicers per hour.
The plant operates 24/7,24 hours a day every day of the week.
What is the least amount of monthly capacity you would have to add to the bottleneck(s) to shift the bottleneck to a different process?
A) 2,000,001 juicers per month.
B) 600,001 juicers per month.
C) 1,320,001 juicers per month.
D) 50,001 juicers per month.
Exterior: 100,000 x 30 = 3m
Pulp filter: 25,000 x 24/6 x 30 = 3m
Painting: 48 x 3,000 x 30 = 4,320,000
Packaging: 24 x 5,000 x 30 = 3.6m
Add 600,001 to Exterior and to Pulp Filter,would move the constraint to Packaging
Correct Answer:
Verified
Q37: Bryan Inc.produces a specialty top-quality juice machine.The
Q38: Lens Care Inc.(LCI)manufactures specialized equipment for polishing
Q39: TwoShaft Inc.manufactures a wide variety of parts
Q40: Lens Care Inc.(LCI)manufactures specialized equipment for polishing
Q41: Electronic Component Company is a producer of
Q43: Place the five steps in implementing a
Q44: Bryan Inc.produces a specialty top-quality juice machine.The
Q45: Quality Chairs Inc.(QC)manufactures chairs for industrial use.Laura
Q52: During the sales life cycle, which is
Q53: Which of the following is a common
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents