Xero Company's standard factory overhead rate is $3.75 per direct labor hour (DLH) ,calculated at 90% capacity = 900 standard DLHs.In December,the company operated at 80% of capacity,or 800 standard DLHs.Budgeted factory overhead at 80% of capacity is $3,150,of which $1,350 is fixed overhead.For December,the actual factory overhead cost was $3,800 for 840 actual DLHs,of which $1,300 was for fixed factory overhead.Assuming the use of a two-way breakdown (decomposition) of the total overhead variance,what is the factory overhead efficiency variance for December?
A) N/A-this variance does not exist under a two-way breakdown of the total overead variance.
B) $90 unfavorable.
C) $150 unfavorable.
D) $225 favorable.
E) $425 unfavorable.
Correct Answer:
Verified
Q86: Neptune Inc.uses a standard cost system and
Q87: Bluecap Co.uses a standard cost system and
Q88: Bluecap Co.uses a standard cost system and
Q89: Xero Company's standard factory overhead rate is
Q90: At the denominator activity level,Norland Company's total
Q92: Xero Company's standard factory overhead rate is
Q93: Neptune Inc.uses a standard cost system and
Q94: Bluecap Co.uses a standard cost system and
Q95: Bluecap Co.uses a standard cost system and
Q96: Neptune Inc.uses a standard cost system and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents