You are working on a bid to build two city parks a year for the next three years. This project requires the purchase of $180,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the 3-year project life. The equipment can be sold at the end of the project for $34,000. You will also need $20,000 in net working capital for the duration of the project. The fixed costs will be $16,000 a year and the variable costs will be $168,000 per park. Your required rate of return is 15 percent and your tax rate is 34 percent. What is the minimal amount you should bid per park? (Round your answer to the nearest $100)
A) $72,500
B) $128,600
C) $154,300
D) $189,100
E) $217,600
Correct Answer:
Verified
Q70: Jasper Metals is considering installing a new
Q71: Bernie's Beverages purchased some fixed assets classified
Q72: You just purchased some equipment that is
Q73: Peterborough Trucking just purchased some fixed assets
Q74: Colors and More is considering replacing the
Q75: You own some equipment that you purchased
Q77: Crafter's Supply purchased some fixed assets 2
Q78: Bruno's Lunch Counter is expanding and expects
Q80: The Buck Store is considering a project
Q102: How can two firms arrive at two
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents