Which of the following is true of the triple constraint in projects?
A) The time constraint is the most critical of the three constraints in projects.
B) The three fundamental project constraints are insulated from each other.
C) Changes in one fundamental constraint affect the other constraints as well.
D) Cost constraints take precedence over time and scope constraints in all projects.
Correct Answer:
Verified
Q31: Which of the following functions does a
Q32: A confirmation bias is a rare human
Q33: The stage at which a project is
Q34: The stage at which early phase managers
Q35: Which among the following is the best
Q37: Which of the following is a characteristic
Q38: Which of the following is an accurate
Q39: The _ process lays the groundwork for
Q40: Which of the following best describes a
Q41: In which of the following project management
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents