Which of the following best defines a critical path in a project?
A) the longest project path comprised of tasks that do not affect the finish date if they are delayed
B) the longest project path that identifies tasks that cannot be delayed without affecting the finish date
C) the path obtained by adding the time required for tasks of the shortest duration
D) the shortest path undertaken in a monitoring process in which there is no fixed deadline
Correct Answer:
Verified
Q37: Which of the following is a characteristic
Q38: Which of the following is an accurate
Q39: The _ process lays the groundwork for
Q40: Which of the following best describes a
Q41: In which of the following project management
Q43: Which of the following best describes deliverables
Q44: The term _ refers to products, documents,
Q45: _ track progress from start to finish,
Q46: The _ refers to the longest course
Q47: The _ process in project management focuses
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents