This is zero for all of the first activities on a CPM network diagram.
A) Slack
B) Late start
C) Late finish
D) Early start
E) Early finish
Correct Answer:
Verified
Q54: Activity 7 is directly preceded by two
Q55: Which of the following is not a
Q56: The critical factors in project failure include
Q57: Using PERT,the project completion time closely resembles
Q58: Describe CPM and the critical path.
Q60: List three project management techniques used by
Q61: If a project has an expected completion
Q62: Identify and describe the three different estimates
Q63: Identify five of the critical factors in
Q64: If an activity has an optimistic time