If an assembly process consists of 5 steps in series (activity A,activity B,activity C,activity D,and activity E) ,what is the utilization of the bottleneck activity if A takes 20 seconds,B takes 10 seconds,C takes 30 seconds,D takes 15 seconds,and E takes 5 seconds per unit?
A) 100%
B) 66%
C) 50%
D) 33%
E) 12%
Correct Answer: