A Local Company Supplies City Schools with Supply Packages

Question 62

Essay

A local company supplies city schools with supply packages.How many assembly lines are needed if the company works 10 hours a day during July to meet demand.They wish to have a 20% capacity cushion.How many assembly lines should they have?
A local company supplies city schools with supply packages.How many assembly lines are needed if the company works 10 hours a day during July to meet demand.They wish to have a 20% capacity cushion.How many assembly lines should they have?

Correct Answer:

verifed

Verified

M = ((2400 +120)+ (4500 + 180)...