Petroleum Inc.(PI) controls off-shore oil leases.It is considering the construction of a deep-sea oil rig at a cost of $500 million.The price of oil is $100/bbl.and extraction costs are $50/bbl.PI expects costs to remain constant.The rig will produce an estimated 1,200,000 bbl.per year forever.The risk-free rate is 10% per year,which is also the cost of capital.(Ignore taxes) .Suppose that oil prices are uncertain and are equally likely to be $120/bbl.or $80/bbl.next year.
Suppose that PI has the option to postpone the project by one year.Calculate the value of the real option to postpone the project for one year.
A) +$30 million
B) +$50 million
C) +$54 million
D) +$70 million
Correct Answer:
Verified
Q27: Monte Carlo simulation is likely to be
Q29: One can employ simulation models to
I.understand the
Q31: Hammer Company proposes to invest $6 million
Q32: Petroleum Inc.(PI)controls offshore oil leases.It is considering
Q33: Which of the following does NOT represent
Q37: The following are real options EXCEPT:
A)stock options.
B)timing
Q38: Which of the following simulation outputs is
Q39: The Solar Calculator Company proposes to invest
Q40: Generally,Monte Carlo models,for project analysis,use which device
Q56: Firms with higher fixed costs tend to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents