A project has an expected cash flow of $300 in year 3.The risk-free rate is 5%,the market risk premium is 8%,and the project's beta is 1.25.Calculate the certainty equivalent cash flow for year 3,CEQ3.
A) $228.35
B) $197.25
C) $300
D) $270.02
Correct Answer:
Verified