Which of the following describes the activities appropriately performed by the project team during Perform Qualitative Risk Analysis?
A) Team members assess the probability of occurrence and severity of impact for identified risks.
B) Team members develop contingency plans for all risks to avoid adverse impacts to project objectives.
C) Team members identify potential risk events.
D) Team members define how to conduct risk management activities for the project.
Correct Answer:
Verified
Q17: Risk response strategies such as accept risk
Q18: The purpose of risk management is to
Q19: Sometimes the risks posed by a project
Q20: The risk register is a living document
Q21: On agile projects,detailed risk management activities may
Q23: All of the following criteria can be
Q24: Which of the following describes how the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents