When a project manager asks clarifying questions and paraphrases what is being communicated to them,he or she is using ?
A) Passive listening
B) Active listening
C) Information gathering techniques
D) Soft skills
Correct Answer:
Verified
Q21: In which of the following tools would
Q30: Q33: Q33: Change control includes which of the following Q36: Control quality generally includes all of the Q37: The Budget at Completion (BAC)is the sum Q40: All of the following accurately describe earned Q40: While the manage communications process is underway,effective Q43: Describe how you would adopt a balanced Q44: Your most recent project performance report indicates![]()
![]()