Figure 141 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31

Question 28

Multiple Choice

  Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31, 20XX)  -Consider the project performance report presented in figure 14.1.Your analyst has determined that your estimate to complete (ETC) is $226,000.Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance,what is your estimate at completion (EAC) ?​  A)  $542,000  B)  $550,000  C)  $568,000  D)  It can not be determined from the information provided. Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31, 20XX)
-Consider the project performance report presented in figure 14.1.Your analyst has determined that your estimate to complete (ETC) is $226,000.Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance,what is your estimate at completion (EAC) ?​ 


A)  $542,000 
B)  $550,000 
C)  $568,000 
D)  It can not be determined from the information provided.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents